The renovation and expansion of the historic Jones Library building in the center of downtown is advancing steadily. On the garden level, the underground work has been completed and the next steps will be creating the vapor barrier and concrete floor. All roof decks on the new build portion have been completed, as well as all concrete on the third and second floors. Exterior framing around the new portion is nearly complete.
Preparation for HVAC systems has begun, and the roof will have a sound slab that prevents the sounds from the HVAC system from entering into the building. The projected re-opening time for the library is spring 2027, provided the remainder of the project continues as smoothly as it has thus far!



Generous supporters have brought us closer to our fundraising goal for the project, with donations at all levels. As of May 1, 2026, the Capital Campaign has raised $9,076,025 of its total $15,822,518 goal.
Community members are invited to:
While the Jones is under construction, its temporary space at 101 University Drive is still bustling, along with Amherst’s beautiful branch libraries: the South Amherst Munson Memorial Library and the North Amherst Library. Come visit us!

